Construction of Community Battery at Homburg Reserve to begin
Construction of a new Community Battery at Homburg Reserve is scheduled to commence on Monday, 23 November 2026.
Located at Lot 506 Homburg Drive, Murray Bridge, the project is part of the South Australian Government's emPowering SA program, which aims to support the transition to renewable energy and improve access to affordable electricity.
The community battery will store energy generated from renewable sources and support the local electricity network, helping participating households access the benefits of locally stored energy.
The proposed location was identified by the Department for Energy and Mining due to its proximity to homes expected to benefit from the initiative, existing electricity infrastructure and the availability of suitable space.
The Community Battery will be fully funded and owned by the South Australian Government and operated by an energy retailer. There will be no financial cost to Council or ratepayers associated with the installation or operation of the battery.
Construction activities are expected to continue until 21 December 2027.
Council thanks nearby residents and the wider community for their understanding while construction works take place.
Further updates will be shared as the project progresses.