Murray Princess Wharf Update

Following an incident on Sunday 21 July 2024, that caused damage to the mooring dock at the Murray Princess Wharf, the Murray Princess temporarily paused all visits to Murray Bridge for safety reasons until repairs are completed.

Remediation works will start on Saturday 29 March 2025 to bring the Murray Princess Wharf back to her former glory.

Update Friday 28 March 2025

Repair works will commence on the Murray Princess Wharf on Saturday 29 March 2025 (upstream from the old road bridge).

Works will include:
-Partial demolition of the damaged structural steel components.
-Survey works to commence week of Monday 30 March 2025.
-Water and land access to the site during works will be restricted.

While Construction is underway access to the shared path adjacent the site will be temporarily restricted.

Update Friday 1 August 2025

Remediation works on the Murray Princess Wharf are now complete and ready to welcome visitors.

Thanks for your patience while we carried out these essential works.